Projects in progress
The City of NiŠ, through the Office for Local Economic Development, has launched a number of ongoing projects that will continue in the coming years, with a focus on empowering the local community and creating a development base to improve the living conditions of citizens. These projects are implemented with the financial and technical support of the European Union and bilateral donors, such as UNDP, UNOPS, GIZ, but also with the help of financial institutions such as the European Investment Bank, the French Development Agency and others. Once implemented, the City of Niš and the wider community will have multiple benefits.
Road and sidewalk construction in the Lozni kalem complex
Value: 132.154.167,62 RSD
Number of employees: /
Beginning of the project: 2017
The project is funded with co-financing by the Ministry of Economy per a Call – Let’s Build Together (EIB). The funds of the Ministry of Economy are 55,064,167.76 RSD , VAT excluded (50%), and the amount of 77,089,834.86 RSD, VAT included, is funded by the City of Niš.
The project envisaged and has implemented construction of six streets with sidewalks and horizontal and vertical signaling for a total length of 2,317 m.
Improvement of the water supply system of villages Knežica, Perutina, Ćurlina and Belotinac -3. phaze
Value: 9.881.027,19 RSD
Number of employees: /
Beginning of the project: /
The third phase of the project is related to the construction of primary and secondary water supply network in the villages of Ćurlina, Knežica and Perutina, as well as the construction of a pumping station in Perutina.
By the Contract on Regulation of Water Supply of villages Knežica, Perutina, Ćurlina and Belotinac – the City of Niš assumed the obligation (Article 5 of the Contract) to build a secondary water supply network in the villages Knežica and Ćurlina, as well as to build a water supply network in the village of Perutina.
The duties of the City of Niš will be implemented in five sub-phases:
- Phase 1 – Construction of the main line towards Knežica and Ćurlina in the length of 715m and part of the line in the direction of Ćurlina in the length of 120m.
- Phase 2 – Construction of a water supply network in the village of Ćurlina
- Phase 3 – Construction of a water supply network in the village of Knežica
- Phase 4 – Construction of a pumping station in Perutina
- Phase 5 – Construction of a water supply network in the village of Perutina
Implementation in 2019, schedules the sub-phase 1 – Construction of the main line towards Knežica and Ćurlina in the length of 715m and part of the lines in the direction of Ćurlina in the length of 120m (estimated values 8.234.189,33 RSD , VAT excluded, and 9.881.027,19 RSD, VAT included).
Other sub-phases (2-5) are scheduled for implementation in 2020 and 2021.
Project ‘’Waste Water Collection and Treatment in the City of Niš“
Value: 66.921.000,00 euro
Number of employees: /
Beginning of the project: /
The total value of the investment is € 66,921,000.00.
Participation in project financing:
- EU GRANT – € 47,363,000.00
- Ministry of Environment Protection- € 8.787.000,00 €
- City of Niš: – € 886.000,00 €
- RWC loans – € 9,885,000.00
The Swedish International Development Cooperation Agency (SIDA) and the Delegation of the European Union to the Republic of Serbia are financing the development of project documentation (contract value: € 805,000.00).
Construction of wastewater treatment plant and additional sludge treatment and completion of works on the collector network of the city (14.1km) with reconstruction of the collector in Niš, expansion of the collector network (23.0km) and construction of a drinking water treatment plant on Mediana – treatment of filter wash water
The project consists of six components:
- The City of Niš wastewater treatment plant – location Ciganski ključ
- The City of Niš wastewater treatment plant – additional oil treatment
- Main collectors to the City of Niš Wastewater Treatment Plant
- Reconstruction of collectors in Niš
- Expansion of the collector network
- Drinking water treatment plants Mediana – treatment of filter wash water
Property-legal transactions along the routes of the planned collectors have been completed (391 decisions passed)
Conceptual designs for both plants were developed: the Main plant in Ciganski ključ and the Mediana Plant.
The Urban Design Project has been developed and approved (the design of the PE Urban Planning Institute Niš has been confirmed by the Ministry of Construction Transport and Infrastructure (MCTI)
Development of Urban Planning Project for DWTP Mediana is underway.
Design and revitalization of the nis fortress - phase 1
Value: 60.000.000,00 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Ministry of Trade, Tourism and Telecommunications – 100%
City participation : 0,00 RSD
Spent : 43.709.144,04 RSD
In the Amphitheatre toilet facilities were refurbished and new amenities were provided. The stage revitalized, ie the wall cladding was replaced and acoustic panels were installed instead of the wooden paneling, the stage ceiling was repaired from cracks and bumps, as well as the stage floor, which was leveled and covered with a rubber floor covering.
Across the section of the park, just above the summer stage, walkways were formed of granite cube and a new children’s and park mobiles were installed.
The Sports Complex in the entrenchement of the Fortress now consists of a basketball court, four 3×3 basketball courts, a handball court and a long jump track at the end of which is a sand pool. All courts are with concrete granstands that have been completely repaired, repaired, statically stable, safe and ready to receive sports fans. Holes, humps and cracks were repaired on the grounds, all courts were paved and coated with high quality cast tartan.
Virtual presentation of the multilayer cultural identity of a modern Niš
Value: 45.162.076,60 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Ministry of Culture and Information
City participation: 12.162.076,60 RSD
The overall objective of the project is to support cultural activities in Niš, as a driver of social and economic development; systematization and improvement of cultural programs, creative industries as well as cultural infrastructure facilities; adequate use and presentation of cultural heritage assets through research, protection, digitization, participation of the general public and presentation of the creative work of the multilayer cultural identity of modern Niš.
Sub-projects funded by the Ministry of Culture and Information:
- Reconstruction of the National Museum building at the Mediana archaeological site,
- Project of Archaeological Research, Presentation, Planning and Works at Mediana archaeological park,
- Renovation of the Puppet Theater in Niš – Replacement of floors and seats in the theater hall.
Sub-projects financed by the City of Niš:
- Development of the Project of Tourist Presentation of the Mediana archaeological site,
- Preparation of the Protective Structure Project over Terme (thermal baths), which was abandoned during the project implementation,
- Roofing works,
- Implementation of the Tourist Presentation Project of the Mediana archaeological site
- Co-finances part of the funds for the reconstruction of the National Museum building at the Mediana archeological site.
Construction of a shooting range for the needs of a regional school shooting sport
Value: 107.784.000,00 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
City participation: 67.257.000,00 RSD
Participation of the Ministry of Economy: 40.527.000,00 RSD
- Reconstruction and adaptation of part of the ground floor of the building,
- Reconstruction of the existing structure on the ground floor and construction up to the level of completion of the building without equipping for special recreation purposes,
- Building of the floor for a 32-place air weapons shooting range.
Auxiliary premises are: entrance hall, lift platform for people with mobility difficulties, sanitary block for people with special needs, women’s and men’s locker room, weapons and ammunition warehouse, shooter’ club with kitchenette and official premises.
Part of the project are toilets and a sun terrace that serve the outdoor pools, which greatly enhances the functionality of the facility and contributes to the rehabilitation and upgrading of SC “Čair” facilities.
The newly designed facade follows the contemporary form of the building, where the structural facade and decorative lighting give an extraordinary impression. Slanted “slots” create the illusion of a bullet trajectory that reflects the firing range space. The game of materialization on the facade was accompanied by illumination, which has programmed ignition and shut-down intervals, as well as discoloration.
The implementation of this project will enable the City of Niš to host many International sports competitions and national championships in all categories, as a rule of the World Federation, which would make the City of Niš recognized as a city of sports in Serbia and the region.
Rehabilitation, reconstruction and improvement of energy efficiency in Elementary school "Vožd Karadjordje" in Niš
Value: 181 038 942, 62 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Public Investment Management Office : 156.258.000,00 RSD
City participation: 0,00 RSD
Anticipated deadline: 2020
The works on rehabilitation, reconstruction and improvement of the energy efficiency of the facility are executed in order to improve the conditions of use of the facility, repair and replacement of certain damaged parts of the installation and equipment and to increase the energy efficiency of the facility.
The project comprises: replacement of existing exterior and interior joinery, facade repair on the part of the building under the protection of the Institute for Protection of Cultural Monuments Niš, replacement of damaged gutters and sills, replacement of floors, rehabilitation and repair of interior walls with installation of parapet wall claddings, installation of suspended ceilings in hallways, classrooms and auxiliary premises, reconstruction of existing toilets, construction of a new toilet in the attic, construction of an energy efficient façade on the part of the building that is not under the protection of the Institute for Protection of Cultural Monuments Niš, rehabilitation and reconstruction of the roof on the part of the extension to the gym, rehabilitation of the partition in the school yard, adaptation of electrical installations, addressable fire alarm system, energy rehabilitation HVAC installations, landscaping the yard …
Renovation, rehabilitation and improvement of energy efficiency of "Svetozar Marković" High School in Niš
Value: 93.921.224,00 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Public Investment Management Office : 97.521.600,00 RSD
City participation: 0,00 RSD
Anticipated deadline: mid 2020
The renovation, rehabilitation, energy efficiency improvement and investment maintenance of the Svetozar Marković High School in Niš are being carried out in order to improve the conditions of use of the facility, change the organization of space in a part of the facility, repair and replacement of certain damaged parts of the installation and equipment.
The project includes: replacement of damaged floors in classrooms, corridors, entrance, staircase, hall by floors and toilets, reconstruction of existing toilets, replacement of interior joinery, reconstruction of the gym and locker rooms, construction of the energy facade, smoothing and painting of premises after all installation work, renovation of basement rooms, making of elevators for persons with disabilities, reconstruction of HVAC installations, ventilation of the gym, air conditioning on the fourth floor assembly hall , landscaping the yard ..
Reconstruction, renovation and evergy rehabilitation of the Children and Youth Center Duško Radović in Niš
Value: 79.622.800,00 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Public Investment Management Office: 79.622.800,00 RSD
City participation: 0,00 RSD
Anticipated deadline: mid 2020
The reconstruction, renovation and energy rehabilitation of the Children and Youth Center ” Duško Radović ” in Niš is being carried out in order to improve the conditions of use of the facility, repair and replacement of certain damaged parts of the installation and equipment and increase the energy efficiency of the facility.
The project includes: replacement of flooring in auxiliary buildings used by Dom Duško Radović and Center for Family Accommodation and Adoption, rehabilitation and painting of interior walls and ceilings, replacement of interior joinery, replacement of existing exterior joinery in basement, reconstruction of existing toilets, improvement of energy efficiency of the facade, replacement of roof structure and cladding, replacement of gutters and sills, repairs of fences, replacement of installations of water supply and sewerage, reconstruction of existing lighting, A/C installations, reconstruction of HVAC installations …
Project of Niška Banja public park maintenance
Value: 29.034.196,00 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Ministry of Trade, Tourism and Telecommunications 15.000.000,00 RSD
Participation of the City of Niš, Public enterprises, Parking service, Municipality of Mediana and Municipality of Niška Banja: 14.034.196,00 RSD
Anticipated deadline: August 2019
The project envisages the current maintenance of a public park in Niška Banja (a park with a square between the Zelengora Stationary and the Old Bath). The goal is to accentuate cultural, historical and natural resources by opening the line of sight and landscaping.
It is planned to replace and install a new tiling on the plateau around the garden fountains- pools, between the Zelengora Stationary and the Old Bath. The tiling is made of concrete slabs similar to the existing ones in the park, with the formation of pedestrian-tailored paths that also contribute to the playfulness of the parterre..
Sufficient number of benches are set up along the footpaths. Existing broken and damaged benches are replaced with new ones in order to achieve uniformity. The free areas are arranged in accordance with the existing ones and planted with grass and ornamental shrubs.
The fountain, as the central motif of the space, is emphasized by the parterre, but also by the appropriate automatics in order to achieve the designed effects. It is also envisaged to replace the old lighting and cables on the plateau.
Extension of special classrooms and gyms in Elementary school "Miroslav Antić"
Value: around 90.000.000 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Funding source: Ministry of Economy
Value of the basic contract for the construction of the hall 77.994.726,16 RSD, VAT included, value of the contract for thermal insulation of the facade 7.573.248,56 RSD, VAT include.
Participation of the City of Niš in the project: 22.903.398,72 RSD (total unforeseen works, VAT include, plus VAT for works in the basic contract)
Construction work on the upgrade of the Elementary school “Miroslav Antić” began in 2012, continued in 2016 and is now coming to its end. The works relate to the construction of a complete new part of the school which is connected with the old part of the building by a warm connection. The new part of the school, with its own entrance, consists of several special classrooms connected by a unique hallway with a newly built gym. In addition to all of the above works, there are additional works completed in 2018 that concerned the installation of thermal insulation on the facade, floors and ceilings as improvements to the energy efficiency of the facility.
After the delay in works, it is expected that the construction will be completed through a change in the manner of realization of mechanical installations in the facility.
Reconstruction of facades in the City of Niš - 2. phase
Value: 14.012.419,54 RSD
Number of employees: /
Beginning of the project: /
Implementation leader: City of Niš, OLED
Participation of the City of Niš in the project: 14.012.419,54 RSD
Anticipated deadline: December 2019.
The reconstruction includes „Djoka Jovanović Legacy“ building and the Stevan Sremac National Library – a new part of the building. The buildings are under the protection of the Institute for the Protection of Cultural Monuments of Niš.
„Djoka Jovanović Legacy“ is a multy floor building built in the early 20th century in the city center. The building is the property of the City of Niš and is the seat of the City Attorney.
The Stevan Sremac National Library building is one of the oldest cultural institutions in the city and the first public library in Southern Serbia. Phase I – Lot I – reconstructed part of the former municipal administration building hosting the National Library since 1959. Lot II – Phase I covers the part of the building that was built at the end of the 20th century and is an integral part of the library complex.
The restoration and conservation works are being carried out, the rehabilitation of the facilities and the current maintenance according to the condition of the buildings, as well as the installation of decorative lighting on the „Djoka Jovanović Legacy” building.
Econstruction of the science -technology park building in Niš
Value: RSD 1 200.000.000
Number of employees: /
Beginning of the project: /
Implemented by: City of Niš, Office for Local Economic Development
Contribution of the City of Niš to the project: RSD 30.000. 000
Expected completion date: May 2020.
The construction of the Science Technology Park building is financed by the funds of the Republic of Serbia, and the Contract on the implementation and funding of the project “Construction of the Science Technology Park in Niš“ signed by the Ministry of Education, Science and Technological Development, the Public Investment Management Office, the Cabinet of the Minister of Innovation and Technological Development and the City of Niš, stipulates the following obligations of the City of
Niš:
- Provides administrative, professional and technical support to all signatories to this Contract
- Supervises the Project for Execution (Main Design) (PZI)
- Provides the Main Fire Protection Design
- Obtains the approval of the technical documentation by the regional unit of the state administration body in charge of fire protection
- Funds and provides for the development of preventive measures action plans, and provides a safety coordinator at the execution stage
- Funds and provides technical inspection of the facility and transformer substation
- Funds and builds the missing infrastructure in accordance with the location
conditions - Funds and provides the design supervision over the project implementation
The City of Niš fulfilled all its due obligations (items 2,3 and 4), and duly fulfills its
current obligations related to the construction of the facility dynamics (items 1, 5,6,7 and 8) and duly submits reports to the competent Ministry.
Construction of the missing infrastructure includes the construction of the missing
electricity infrastructure and water and sewage infrastructure.
For the construction of the missing electricity infrastructure, a public procurement
procedure is underway to select a contractor. The expected completion date for these works is March 2020.
For the construction of the missing water and sewage infrastructure, the process of
possession of site and commencement of works of the contractor is underway. The expected completion date for these works is March 2020.
Reconstruction of the heat substations in the pool and equipment room facility in the complex of Čair sport-recreation center in Niš
Value: around 6.000.000 RSD
Number of employees: /
Beginning of the project: /
Implemented by: City of Niš, Office for Local Economic Development
Contribution of the City of Niš to the project is RSD7.800.000.
Expected completion date: April 2020.
The 2020 plan is to terminate the existing „Čair“ boiler room that uses crude oil, which is an uneconomic and exceptional environmental pollutant, and to connect its customers to the new modern „Clinical Center“ boiler room that uses economically and environmentally friendly natural gas.
Reconstruction and adaptation of existing thermal substations in the swimming pool facility and equipment room at SRC “Čair” in Niš is due to the change of heating regime (pressure and temperature) from the previous direct system from the existing “Čair” boiler room to the indirect system from the new “Clinical Center” boiler room.
A public procurement procedure is underway to select a contractor.